At the Common Council meeting held October 25th, the City of Muskego approved a design services contract for a recreation trail to be planned and ultimately built along the north side of Woods Road, from Racine Avenue to Quietwood Creek Drive. This contract, which entails all necessary survey and design work for the Woods Road recreation trail, was awarded to Graef.
Currently, Graef is performing trail survey work and wetland delineation analysis during the month of November.
Construction is anticipated to occur in the summer of 2012, when school is out for summer. We anticipate that a preliminary design will be completed and a Public Information Meeting scheduled early this winter, prior to which, affected residents will receive a mailing informing them of the meeting date and time.
Preliminary Schedule of Milestones:
Preliminary Design Work November – December
Environmental Documentation & Agency Concurrence November – March
Public Information Meeting January 23, 2012
5-6:30 p.m. (City Hall)
Final Design January – March
Bidding April
Trail Construction June – August
Please stop back for monthly project updates.
Project information will be available on the city’s website as it becomes available at www.ci.muskego.wi.us/woodsroadtrail.